Meet with Arnold,
New Front Entrance
is scheduled to open
3:00pm Friday,
November 6, 2009
The Railings
are installed
HPL re-OPENed, using the SIDE-DOOR,
on Thursday, September 10, 2009,
as planned.
Construction of the NEW
Entrance and Front Stairs
will take a few weeks,
which is expected to be
completed with the installation
of the NEW Railings
around end of October
or now probably November;
but,
HPL is OPEN!2009-10-26 Mon
Almost Completed...
Click the photo for LARGER view.2009-10-26 Mon
... except, for the Railings,
which are being made to fit
the holes that have been drilled
and can be seen in this photo
and the previous photo.
Click the photo for LARGER view.2009-10-05 Mon
Bricks and Stonework
are being applied
Click on PHOTO for LARGER view2009-09-22 Tue
A Layer of Gravel
is atop the Concrete Blocks
with
Wooden Forms
in place
ready to for a
Layer of Concrete.
Click on PHOTO for LARGER view2009-09-17 Thu
Click on PHOTOs for LARGER view
The Foundation
of Concrete Blocks
for the
NEW Entrance and Stairs
was added atop
the Concrete Footing
poured on Tue.
Plywood atop the
Concrete Blocks
is a temporary
protective covering.
2009-09-13 SunDemolition
of the old front stairs
was completed, to prepare
for NEW FRONT STAIRS.
HPL re-OPENed, using the SIDE-DOOR,
on Thursday, September 10, 2009,
as planned.